Data Center Campus

PW Digital Gateway

CRITICAL RISK ACTIVE LITIGATION

The largest data center battle in America. 37 planned data centers adjacent to Manassas National Battlefield Park. Rezoning overturned by court in August 2025. Virginia Court of Appeals barred construction in November 2025.

9.5
Risk Score
CRITICAL
Location
Prince William County, VA
Investment
$24.7 Billion
Developers
QTS, Compass, others
Status
Rezoning Overturned

Risk Signal Breakdown

Raw Score: 12.67 → Normalized: 9.5/10

Timeline

November 2023
Lame-duck Board of Supervisors approves trio of rezonings for Digital Gateway
January 2024
Coalition to Protect PWC and American Battlefield Trust file lawsuits challenging rezoning
October 2024
Judge Tracy Hudson holds hearing on demurrers
August 2025
MAJOR: Judge rules zoning for Digital Gateway VOIDED
September 2025
Developers announce intent to appeal
November 2025
MAJOR: Virginia Court of Appeals bars construction until legal challenge concludes
December 2025
County approves additional $400K for litigation costs