offshore wind - regional

New England Offshore Wind Crisis

📍 MA, RI, CT ⚡ 5,000+ MW at risk 💰 $20+ billion 📅 Updated: Mar 17, 2026

The New England offshore wind pipeline is in crisis. Contract cancellations, cost overruns, federal permitting freezes, and Trump administration hostility have thrown multiple projects into limbo. Only Vineyard Wind and Revolution Wind are progressing; others face uncertain futures. Massachusetts' 2030 clean energy goals now in jeopardy.

8.5
Risk Score
Critical Risk

Risk Factors

regulatory
9/10
legal
7/10
political
9/10
community
5/10
environmental
4/10
economic
8/10

Analysis: Extreme regulatory and political risk from Trump administration actions (permitting freeze, lease suspensions, COP rescission attempts). Economic risk from rising costs, interest rates, and PPA uncertainty. Only projects under construction have reasonable path forward.

Project Status Dashboard

Project Developer Capacity Status Key Issue
Vineyard Wind 1 Avangrid/Copenhagen 800 MW CONSTRUCTION Blade failures; mid-2026 finish
Revolution Wind Ørsted/Eversource 704 MW CONSTRUCTION Progressing; mid-2026 target
New England Wind 1 Avangrid 791 MW IN LIMBO PPA delayed; COP rescission threat
New England Wind 2 Avangrid 1,080 MW IN LIMBO No PPA; awaiting state solicitation
SouthCoast Wind Ocean Winds 1,287 MW IN LIMBO RI dropped; MA PPA pending
Commonwealth Wind Avangrid 1,232 MW UNCERTAIN Original contract canceled 2023; rebid unclear

Timeline of Crisis

2023
milestone

Vineyard Wind begins construction as first large-scale US offshore wind project

July 2023
economic

Avangrid seeks to cancel Commonwealth Wind PPA citing unsustainable economics from inflation and supply chain costs

Late 2023
economic

Multiple developers request PPA price renegotiations across Northeast; SouthCoast (then Mayflower) contract terminated

September 2024
regulatory

Massachusetts awards New England Wind 1 contract (791 MW) in re-solicitation

November 2024
economic

Vineyard Wind blade failures cause 6-month delay; first power delivery pushed to early 2025

November 2025
political

Rhode Island drops SouthCoast Wind power purchase, shifting full burden to Massachusetts

December 2025
regulatory

Trump administration suspends Vineyard Wind lease (along with 4 others); seeks to rescind Avangrid Construction and Operations Plan

December 2025
milestone

Vineyard Wind reaches 62/62 turbines installed despite lease suspension; power production continues

January 2025
regulatory

Federal permitting freeze on January 20 (inauguration); SouthCoast NOAA fisheries permit blocked

January 2025
legal

Federal judges temporarily block some lease suspensions; legal battle ongoing

February 2026
political

Massachusetts announces Nova Scotia partnership for potential transmission backup if projects stall; ISO-NE warns of reliability risks

Developer Status

Avangrid

Projects: Vineyard Wind 1, New England Wind 1 & 2, Commonwealth Wind
Total Capacity: ~3,900 MW

Status: Vineyard nearing completion but facing lease suspension. New England Wind fully permitted but PPA delayed multiple times (June 30 deadline). Trump COP rescission creates existential uncertainty. Also awarded Gulf of Maine floating turbine leases in late 2024.

Ocean Winds (SouthCoast Wind)

Project: SouthCoast Wind (formerly Mayflower)
Capacity: 1,287 MW

Status: Received major federal approval January 2025 but awaiting NOAA fisheries permit (blocked). Rhode Island dropped purchase in November 2025. Entire offtake burden now on Massachusetts. PPA deadline June 30. Federal permitting freeze creates limbo.

Key Risk Factors

Political Landscape

Trump Administration

Position: HOSTILE

  • Federal permitting freeze January 20, 2025
  • "Wind memo" creating uncertainty
  • Lease suspensions for 5 projects
  • Seeking to rescind approved COPs

Massachusetts

Position: SUPPORTIVE

  • New tax incentives for supply chain
  • Nova Scotia partnership for backup
  • Continued solicitations despite chaos
  • 2030 clean energy goals at risk

What's Actually Working

Vineyard Wind 1

Despite lease suspension and blade issues, all 62 turbines installed by December 2025. Power production allowed to continue. First power delivered early 2025. Mid-2026 full commercial operation expected. Proves offshore wind works technically, but regulatory war continues.

Revolution Wind

Most turbines installed by December 2025. On track for mid-2026 completion. 704 MW for 350,000 homes. Less federal interference than other projects so far. Ørsted/Eversource partnership provides financial stability.