โœ… PROJECT COMPLETED, Energized September 26, 2024. This page serves as a case study in overcoming opposition.
transmission

Cardinal-Hickory Creek

๐Ÿข ATC / ITC Midwest / Dairyland Power ๐Ÿ“ WI, IA โšก 345 kV / 102 miles ๐Ÿ’ฐ $655 million ๐Ÿ“… Updated: Mar 17, 2026

A 102-mile 345-kV transmission line connecting the Cardinal Substation in Dane County, Wisconsin to the Hickory Creek Substation in Dubuque County, Iowa. Enables delivery of 24+ GW from 161 renewable energy projects across the Upper Midwest. Completed despite years of environmental opposition and federal litigation.

3.0
Risk Score
Completed

Risk Factors (Historical)

regulatory
2/10
legal
5/10
political
2/10
community
4/10
environmental
6/10
economic
1/10

Analysis: Primary opposition focused on environmental concerns about the Upper Mississippi River National Wildlife Refuge crossing. Strong regulatory and political support enabled completion despite federal lawsuit.

Timeline

2011
milestone

MISO includes project in transmission portfolio as Multi-Value Project (MVP)

August 2019
regulatory

Wisconsin PSC approves Western-North and Eastern-South routes (Docket 05-CE-146)

April 2021
milestone

Construction begins following all major permits secured

October 2023
regulatory

All environmental reviews and permitting completed; USFWS approves land exchange for refuge crossing

December 2023
milestone

Eastern half of line energized; 161 renewable projects (24.7 GW) now have transmission path

March 2024
legal

Conservation groups file federal lawsuit challenging refuge segment, alleging unlawful land exchange and NEPA violations

May 2024
legal

Federal appellate court allows construction to proceed despite pending lawsuit

September 26, 2024
milestone

Full energization achieved; project enters commercial service 13 years after MISO recommendation

Opposition Groups

Conservation Coalition

MEDIUM
Environmental WI

Coalition of environmental groups focused on protecting Upper Mississippi River National Wildlife Refuge from transmission line crossing

federal litigation NEPA challenges media campaigns

Local Property Owners

LOW
Landowner WI, IA

Property owners along route concerned about visual impacts and easement compensation

PSC testimony media

Legal Challenges

Refuge Crossing Lawsuit

Court: Federal District Court Pending (but construction allowed)

Claims: Unlawful land exchange with U.S. Fish and Wildlife Service; NEPA violations regarding environmental review of refuge segment

Significance: Despite lawsuit, May 2024 appellate ruling allowed construction to proceed. Project completed while case remains technically open.

Key Arguments Against

Why Project Succeeded (Lessons Learned)

Project Impact

Renewable Enablement

Unlocks delivery of 24+ GW from 161 renewable energy projects across the Upper Midwest to load centers.

Grid Reliability

Eliminates 13 upgrade projects to lower-voltage lines, saving $151 million and improving regional reliability.