Good morning. U.S. factories are losing power fights to data centers, Enbridge restricted Bakken shipments and Energy Vault closed $78 million for a Texas battery.

Top Stories

ENBRIDGE RESTRICTS BAKKEN SHIPMENTS AFTER CONTAMINATION
KFYR
Organic chlorides that can damage refinery equipment were found in crude entering the North Dakota Pipeline. Enbridge is accepting clean barrels under limits while producers reroute some supply to Dakota Access and Bridger.

NORTH CAROLINA PULLS 20 DATA-CENTER DEALS UNDER NEW RULES
WRAL
About 20 previously signed agreements that could have escaped Duke's proposed settlement now face the safeguards. The rules require 10-year minimum contracts, 75% minimum-demand payments and security against stranded infrastructure costs.

PECO'S ELECTRIC SUPPLY RATE JUMPS 10.3%
The Philadelphia Inquirer
The Dec. 1 increase lifts the average 700-kWh residential bill by about $9 a month. PECO points to higher wholesale costs after PJM's summer capacity auction fell 6,800 MW short of its target.

ENERGY VAULT CLOSES $78 MILLION FOR A TEXAS BATTERY
Mercom India
The financing covers construction of the 150-MW, 300-MWh SOSA Energy Center in Madison County. The merchant ERCOT project is targeting commercial operation in the third quarter of 2027.

DOE BACKS DEEP NUCLEAR-WASTE DISPOSAL WITH $20 MILLION
ExchangeMonitor
Deep Isolation says a three-year ARPA-E agreement will move its Universal Canister and deep-borehole system from prototype work toward commercialization. A field pilot is planned in Cameron, Texas.

Power & Grid

SPP CANCELS AN $89.5 MILLION TRANSOURCE LINE
Oklahoma Energy Today
The grid operator dropped the nearly 40-mile Matthewson-Redbud project. Transource's Beckham County-Potter and Sooner-Wekiwa 345-kV lines remain active.

UTAH CLEAN-ENERGY PROGRAM ADDS $4 A MONTH
KUTV
Customers in 16 communities will be enrolled automatically beginning in January. They may opt out free through May 1 or pay $30 later as the program pursues 200 MW to 300 MW of solar by 2028.

DATA CENTERS DRIVE WISCONSIN'S 40% PEAK-DEMAND JUMP
Wisconsin Public Radio
A state assessment says three data centers account for more than 70% of expected peak-demand growth through 2032. Utilities are planning 14.4 GW of new capacity, led by solar and gas.

FERC GIVES MISO'S BACKLOG NEW EXIT RAMPS
Utility Dive
FERC approved penalty-free withdrawals and a one-restudy limit for MISO's 2022 interconnection cycle. The cycle holds about 35 GW among a broader queue of nearly 600 projects and 125 GW.

PLUG-IN SOLAR SPREADS BEYOND THE BALCONY
Bloomberg
More than 10 states now allow small panels that connect to a household outlet. The systems are giving renters and apartment residents a new route to trim utility bills without a rooftop installation.

Data Centers

DATA CENTERS ARE WINNING THE FIGHT FOR FACTORY POWER
Bloomberg
Power constraints are pitting computing campuses against industrial redevelopment across the U.S. In Massena, New York, the closure of an Alcoa smelter erased 84,000 metric tons of annual aluminum capacity.

OFF-GRID DATA-CENTER GAS PLANS TOP 115 GW
MIT Technology Review
Cleanview counted more than 100 U.S. projects, with 4.9 GW operating and 15.8 GW under construction. Developers are turning to on-site generation as grid connections lag.

SHELBY COUNTY ADVANCES DATA-CENTER WATER AND POWER RULES
Local Memphis
Commissioners passed a first reading 9-4 of an ordinance that bans evaporative cooling and phases out carbon-based electricity for large data centers. It does not include a moratorium.

WARRICK COUNTY CREATES A FLOATING DATA-CENTER DISTRICT
WEHT
Each project will require public zoning review and disclosure of infrastructure demands, impacts and safeguards. A 180-day moratorium on applications stays in effect until Feb. 7.

BREWER PROTESTS A HIGHER DATA-CENTER POWER LIMIT
Maine Beacon
Residents rallied against an ordinance that would raise the city's data-center limit from 20 MW to 50 MW. The City Council is scheduled to take its first vote Dec. 8.

Stat of the Day

152M

Additional metric tons of annual U.S. carbon emissions if all announced off-grid data-center gas plants are built
BloombergNEF estimates the difference compared with supplying the same load from the grid in 2035.
MIT Technology Review ↗